Team Capacity Calculator
Calculate available hours from schedules and entered exclusions.
How Team Capacity Calculator Works?
The Team Capacity Calculator works by multiplying team members by scheduled hours and subtracting leave, holidays, meetings, and other exclusions.
-
1. Set scheduled hours
Note hours per person per period, such as 80 hours for a 2-week sprint.
-
2. Multiply by headcount
5 people × 80 hours = 400 gross hours.
-
3. Subtract exclusions
Remove 24 hours of leave, 40 hours of holidays, and 50 hours of meetings = 114 hours.
-
4. Apply a focus factor
286 net hours × 80% focus = 228.8 plannable hours.
Team Capacity Calculator Formula
The Team Capacity Calculator formula is capacity = (people × scheduled hours − exclusions) × focus factor.
- Gross = people × scheduled hours
- Net = gross − leave − holidays − meetings
- Plannable = net × focus factor
- Per person = plannable ÷ people
Example: 5 people × 80 hours − 114 hours of exclusions = 286 hours, and × 0.8 = 228.8 plannable hours (45.8 per person).
Team Capacity Calculator Conversion Table
The Team Capacity Calculator conversion table shows capacity for a 2-week sprint at 80 scheduled hours per person and 10 meeting hours per person.
| Team Size | Gross Hours | Minus Meetings | × 80% Focus | × 70% Focus |
|---|---|---|---|---|
| 3 | 240 | 210 | 168 | 147 |
| 5 | 400 | 350 | 280 | 245 |
| 7 | 560 | 490 | 392 | 343 |
| 9 | 720 | 630 | 504 | 441 |
| 12 | 960 | 840 | 672 | 588 |
What is Team Capacity Calculator?
A Team Capacity Calculator is a tool that calculates the hours a team can realistically commit to work in a period.
Capacity is always lower than headcount × schedule. Leave, holidays, meetings, support duty, and context switching reduce plannable time, and agile teams plan at 60% to 80% of gross hours.
Capacity planning prevents overcommitment. A team that plans 400 hours of work against 229 plannable hours misses its sprint goal by design.
What are the uses of Team Capacity Calculator?
There are 5 main uses of the Team Capacity Calculator, including sprint planning, hiring decisions, and holiday planning.
Sprint planning
Scrum teams set sprint commitments from capacity.
Hiring decisions
Leaders compare demand with capacity before hiring.
Holiday planning
Managers check capacity across peak leave weeks.
Roadmap planning
Product teams match roadmap scope with quarterly capacity.
Support rotations
Teams remove on-call hours from project capacity.